After five days of repair work, a new stretch of asphalt approximately 50 metres long has appeared on the bridge at the Petropavlovsk hydroelectric complex. At the same time, the approaches to the structure and the main part of the road on the dam remain covered in deep potholes.
WHAT WAS REPAIRED AT THE HYDROELECTRIC COMPLEX
According to the Telegram channel «HALYQSTAN», before work began, the bridge at the Petropavlovsk hydroelectric complex was completely closed for routine repairs to the road surface. Cars and lorries were diverted around the site via the city and suburban routes.
After the five days of work were completed, drivers saw a short section of fresh asphalt around 50 metres long. The other long-standing potholes on the road remain.
WHY DRIVERS EXPECTED A LARGER SCOPE OF WORK
The condition of the road at the hydroelectric complex had previously caused discontent among motorists. Because of the deep holes, drivers were forced to slow down and negotiate the section carefully to avoid damaging their vehicles.
Drivers had expected that, after the bridge was fully closed, the road surface would be put in order over a longer stretch. However, immediately after the end of the new asphalt, vehicles once again hit the damaged part of the road.
WHO WAS RESPONSIBLE FOR CARRYING OUT THE REPAIRS
The materials provided state that the work is connected with the North Kazakhstan branch of the Republican State Enterprise «Kazvodkhoz» and the contractor KZYLTU GROUP LLP.
The cost of the repairs, according to the initial information, was 5 million tenge. However, documents on the actual volume of work carried out and a detailed estimate are not included in the materials.
WHAT QUESTIONS REMAIN UNANSWERED
It is not specified which section of the road was supposed to be repaired under the contract or exactly what work was included in the 5 million tenge cost.
There is also no information on whether the repairs have been fully completed or whether additional work is planned at the site. Without technical documentation, it is impossible to determine whether the actual result complies with the terms of the contract.