In the Pavlodar Region, an illegal transfer of KZT 45 million to a contractor for the repair of a section of an intra-village road that was in fact never carried out has been uncovered. A criminal case has been opened on the facts.
HOW THE VIOLATION WAS UNCOVERED
According to the Pavlodar Region Prosecutor's Office, the violation was detected by the Uspensky District Prosecutor's Office during an inspection of the legality of road construction and repair.
It was established that the office of the akim of the Uspensky rural district transferred KZT 45 million to LLP «MKK-Elit Stroy» for the repair of a section of an intra-village road that the contractor did not carry out.
WHO IS INVESTIGATING THE CRIMINAL CASE
On the facts of the uncovered violation, the prosecutor's office opened a criminal case against officials of the akimat and the contractor. The case is being investigated under Article 189 of the Criminal Code of the Republic of Kazakhstan («Misappropriation or embezzlement of entrusted property of others»).
The investigation is being conducted by the Pavlodar Region Department of the National Security Committee (NSC Department).
WHAT IS KNOWN ABOUT THE PROGRESS OF THE INVESTIGATION
Details of the criminal case have not yet been disclosed. The prosecutor's office explained that other information is not subject to disclosure in accordance with Article 201 of the Criminal Procedure Code of the Republic of Kazakhstan.
CONTEXT
In February 2026, in the West Kazakhstan Region (WKR), violations were uncovered during road repairs in the village of Zhumpty. According to the investigation, the contractor drew up certificates containing inaccurate information about the work performed. The contract amounted to KZT 259 million, and the estimated damage to the budget reached KZT 56.5 million.
Another case was investigated in April 2026 in Petropavlovsk. It concerned the construction of a flyover worth KZT 5.4 billion. According to the investigation, the contractor and officials of the customer drew up certificates containing inaccurate data about the work performed. The preliminary damage exceeded KZT 2 billion.
An earlier audit established violations worth KZT 1.5 billion in the construction department of the akimat of Taraz. Among them were additional payments to contractors for work not previously performed, as well as violations in amending the asphalting project for the «Buryl» residential area. Following the inspection, instructions were given to restore the unperformed volumes of work to the specified amount.